Analysis of Production Delays in Children's Game Rides Using the Fault Tree Analysis (FTA) Method

Analisis Keterlambatan Produksi Wahana Permainan Anak Menggunakan Metode Fault Tree Analysis (FTA)

Authors

  • Mochamad Fariz Prayoga Universitas Muhammadiyah Sidoarjo
  • Boy Isma Putra Universitas Muhammadiyah Sidoarjo

DOI:

https://doi.org/10.21070/r5z41g64

Keywords:

Production Delay, Raw Materials, Fault Tree Analysis, Inventory Management, Supply Chain

Abstract

General Background: Manufacturing industries frequently encounter production delays that create schedule uncertainty, elevated operational costs, and reduced organizational performance. Specific Background: Manufacturing facilities producing children's playground equipment experience recurring disruptions driven by raw material availability issues and supply chain instability. Knowledge Gap: Traditional manufacturing operations often lack structured root-cause diagnostic tools to isolate supply-chain bottlenecks from internal machine or labor failures. Aims: This study examines the factors causing production delays in a children’s play-ride manufacturing industry using the Fault Tree Analysis method. Results: The findings demonstrate that delays are triggered by raw material delivery mismatches, limited buffer stock, and supplier distribution constraints, resulting in production halts across molding, painting, and assembly stages. Novelty: This research establishes a structured Fault Tree Analysis framework applied specifically to children's play-ride manufacturing to map basic events such as uncoordinated scheduling and supplier distribution failures. Implications: Implementing optimized safety stock levels and integrated material scheduling systems enables industrial managers to mitigate delay risks and improve production planning.

Key Findings Highlights

  1. Production delays in children's play-ride manufacturing are primarily triggered by raw material delivery mismatches, supplier distribution constraints, and limited buffer stock availability.
  2. Fault Tree Analysis identifies basic events such as uncoordinated material scheduling among workers and supplier instability that cause operational halts during molding, painting, and assembly.
  3. Recommended improvements include optimizing safety stock levels, establishing an integrated material scheduling system, and evaluating supplier performance.

Keywords Production Delay, Raw Materials, Fault Tree Analysis, Inventory Management, Supply Chain

 

References

[1] I. R. Pratama, “Analisis Keterlambatan Proyek Produksi Kereta Dengan Metode Fishbone Diagram,” vol. 16, no. 1, pp. 161–170, 2023.

[2] S. Makhmudah et al., “Optimasi Manajemen Keterlambatan Pengadaan Komponen Mengunakan Root Cause Analysis di Perusahaan Manufaktur,” vol. 6, no. 9, pp. 3642–3649, 2025.

[3] D. Lorenza and T. Rahman, “ANALISIS PENYEBAB KETERLAMBATAN PROSES PRODUKSI PROYEK CRADLE DENGAN METODE FAULT TREE ANALYSIS ( FTA ),” vol. 1, no. 2, pp. 36–42, 2023.

[4] U. Sugiyanto and H. Kurnianingsih, “Analisa Faktor-Faktor yang Mempengaruhi Delay Produksi di PT Konimex,” vol. 4, no. 4, pp. 2544–2551, 2025.

[5] D. Di, P. T. Ravana, J. Dengan, M. Fmea, and D. A. N. Fta, “1 , 2 , 3,” vol. 8, 2025.

[6] A. Suryaningrum, H. Rudianto, A. Mahmudi, and E. K. O. Prasetyo, “ANALISIS FAKTOR PENYEBAB KETERLAMBATAN MENGGUNAKAN METODE FAULT TREE ANALYSIS ( STUDI KASUS PEMBANGUNAN OFFICE HEADQUARTER SURABAYA ),” vol. 2, no. 1, pp. 18–29, 2024.

[7] R. R. Deri, W. Maulani, and P. Gunawan, “Perencanaan Persediaan Bahan Baku Untuk Menghindari Resiko Keterlambatan Produksi Produk Karet Compound Menggunakan Metode Material Requirement Planning ( MRP ),” vol. 9, no. 1, pp. 269–280, 2023.

[8] J. Abdimas, S. Suko, P. Untuk, and M. Ekonomi, “a b i y a s a,” vol. 2, no. 1, pp. 62–67, 2022.

[9] J. K. Marsnata and S. Junaidi, “Tinjauan Steam Toys Untuk Usia 3-6 Tahun dalam Pemenuhan Karakteristik dan Tumbuh Kembang Anak di Indonesia Pendahuluan,” vol. 2, pp. 52–73, 2025.

[10] M. R. Kurniawan, A. S. Cahyana, B. I. Putra, S. Babaev, and M. Junaedi, “Pr Pr f,” pp. 0–9, 2022.

[11] R. Alfianidah and A. G. Prafitasiwi, “Analisis Risiko Penyebab Keterlambatan Pada Proyek Pembangunan Pondasi Silo Phase 3 Ø 24 , 50 M Menggunakan Metode FTA ( Fault Tree Analysis ) Cost And Time Risk Analysis Of Delay Cause In The Construction Project Of Silo Foundation Phase 3 Ø 24 , 50 M Using Fault Tree Analysis,” vol. 01, no. 1, pp. 67–78, 2024.

[12] H. C. W. Abdul Qodir Umri, “Analysis Quality Control of Creamer Product Packaging using DMAIC and RCA Methods [ Analisa Pengendalian Kualitas Kemasan Produk Krimer Menggunakan Metode DMAIC dan RCA ],” ResearchGate, pp. 1–15, 2024.

[13] Y. Saputro and H. C. Wahyuni, “Analysis Quality Control Transformer Using Six Sigma Method And Fault Tree Analysis ( FTA ) Method [ Analisis Pengendalian Kualitas Trafo Menggunakan Metode Six Sigma Dan Metode Fault Tree Analysis ( FTA )],” pp. 1–10.

Downloads

Published

2026-11-22

How to Cite

[1]
“ Analysis of Production Delays in Children’s Game Rides Using the Fault Tree Analysis (FTA) Method: Analisis Keterlambatan Produksi Wahana Permainan Anak Menggunakan Metode Fault Tree Analysis (FTA)”, PELS, vol. 10, no. 1, pp. 3310–3317, Nov. 2026, doi: 10.21070/r5z41g64.

Most read articles by the same author(s)

<< < 1 2