Analysis of Production Delays in Children's Game Rides Using the Fault Tree Analysis (FTA) Method
Analisis Keterlambatan Produksi Wahana Permainan Anak Menggunakan Metode Fault Tree Analysis (FTA)
DOI:
https://doi.org/10.21070/r5z41g64Keywords:
Production Delay, Raw Materials, Fault Tree Analysis, Inventory Management, Supply ChainAbstract
General Background: Manufacturing industries frequently encounter production delays that create schedule uncertainty, elevated operational costs, and reduced organizational performance. Specific Background: Manufacturing facilities producing children's playground equipment experience recurring disruptions driven by raw material availability issues and supply chain instability. Knowledge Gap: Traditional manufacturing operations often lack structured root-cause diagnostic tools to isolate supply-chain bottlenecks from internal machine or labor failures. Aims: This study examines the factors causing production delays in a children’s play-ride manufacturing industry using the Fault Tree Analysis method. Results: The findings demonstrate that delays are triggered by raw material delivery mismatches, limited buffer stock, and supplier distribution constraints, resulting in production halts across molding, painting, and assembly stages. Novelty: This research establishes a structured Fault Tree Analysis framework applied specifically to children's play-ride manufacturing to map basic events such as uncoordinated scheduling and supplier distribution failures. Implications: Implementing optimized safety stock levels and integrated material scheduling systems enables industrial managers to mitigate delay risks and improve production planning.
Key Findings Highlights
- Production delays in children's play-ride manufacturing are primarily triggered by raw material delivery mismatches, supplier distribution constraints, and limited buffer stock availability.
- Fault Tree Analysis identifies basic events such as uncoordinated material scheduling among workers and supplier instability that cause operational halts during molding, painting, and assembly.
- Recommended improvements include optimizing safety stock levels, establishing an integrated material scheduling system, and evaluating supplier performance.
Keywords Production Delay, Raw Materials, Fault Tree Analysis, Inventory Management, Supply Chain
References
[1] I. R. Pratama, “Analisis Keterlambatan Proyek Produksi Kereta Dengan Metode Fishbone Diagram,” vol. 16, no. 1, pp. 161–170, 2023.
[2] S. Makhmudah et al., “Optimasi Manajemen Keterlambatan Pengadaan Komponen Mengunakan Root Cause Analysis di Perusahaan Manufaktur,” vol. 6, no. 9, pp. 3642–3649, 2025.
[3] D. Lorenza and T. Rahman, “ANALISIS PENYEBAB KETERLAMBATAN PROSES PRODUKSI PROYEK CRADLE DENGAN METODE FAULT TREE ANALYSIS ( FTA ),” vol. 1, no. 2, pp. 36–42, 2023.
[4] U. Sugiyanto and H. Kurnianingsih, “Analisa Faktor-Faktor yang Mempengaruhi Delay Produksi di PT Konimex,” vol. 4, no. 4, pp. 2544–2551, 2025.
[5] D. Di, P. T. Ravana, J. Dengan, M. Fmea, and D. A. N. Fta, “1 , 2 , 3,” vol. 8, 2025.
[6] A. Suryaningrum, H. Rudianto, A. Mahmudi, and E. K. O. Prasetyo, “ANALISIS FAKTOR PENYEBAB KETERLAMBATAN MENGGUNAKAN METODE FAULT TREE ANALYSIS ( STUDI KASUS PEMBANGUNAN OFFICE HEADQUARTER SURABAYA ),” vol. 2, no. 1, pp. 18–29, 2024.
[7] R. R. Deri, W. Maulani, and P. Gunawan, “Perencanaan Persediaan Bahan Baku Untuk Menghindari Resiko Keterlambatan Produksi Produk Karet Compound Menggunakan Metode Material Requirement Planning ( MRP ),” vol. 9, no. 1, pp. 269–280, 2023.
[8] J. Abdimas, S. Suko, P. Untuk, and M. Ekonomi, “a b i y a s a,” vol. 2, no. 1, pp. 62–67, 2022.
[9] J. K. Marsnata and S. Junaidi, “Tinjauan Steam Toys Untuk Usia 3-6 Tahun dalam Pemenuhan Karakteristik dan Tumbuh Kembang Anak di Indonesia Pendahuluan,” vol. 2, pp. 52–73, 2025.
[10] M. R. Kurniawan, A. S. Cahyana, B. I. Putra, S. Babaev, and M. Junaedi, “Pr Pr f,” pp. 0–9, 2022.
[11] R. Alfianidah and A. G. Prafitasiwi, “Analisis Risiko Penyebab Keterlambatan Pada Proyek Pembangunan Pondasi Silo Phase 3 Ø 24 , 50 M Menggunakan Metode FTA ( Fault Tree Analysis ) Cost And Time Risk Analysis Of Delay Cause In The Construction Project Of Silo Foundation Phase 3 Ø 24 , 50 M Using Fault Tree Analysis,” vol. 01, no. 1, pp. 67–78, 2024.
[12] H. C. W. Abdul Qodir Umri, “Analysis Quality Control of Creamer Product Packaging using DMAIC and RCA Methods [ Analisa Pengendalian Kualitas Kemasan Produk Krimer Menggunakan Metode DMAIC dan RCA ],” ResearchGate, pp. 1–15, 2024.
[13] Y. Saputro and H. C. Wahyuni, “Analysis Quality Control Transformer Using Six Sigma Method And Fault Tree Analysis ( FTA ) Method [ Analisis Pengendalian Kualitas Trafo Menggunakan Metode Six Sigma Dan Metode Fault Tree Analysis ( FTA )],” pp. 1–10.
Downloads
Published
Issue
Section
Categories
License
Copyright (c) 2026 Mochamad Fariz Prayoga, Boy Isma Putra

This work is licensed under a Creative Commons Attribution 4.0 International License.