Comparative Analysis of Construction Cost Estimates Using SNI and AHSP Methods for the Elevator Shaft Project at RSUD Pindad Turen, Malang Regency
Perbandingan Rencana Anggaran Biaya Metode SNI dan AHSP pada Proyek Ruang Luncur Elevator RSUD Pindad Turen, Kabupaten Malang
DOI:
https://doi.org/10.21070/taezj579Keywords:
Construction Cost Estimation, Unit Price Analysis, Reinforced Concrete Structure, Budget Plan Comparison, Vertical Transportation InfrastructureAbstract
General Background: Construction cost estimation serves as a fundamental instrument in project budgeting and financial planning for building infrastructure. Specific Background: Preparing a reliable Cost Budget Plan (Rencana Anggaran Biaya) requires accurate unit price analyses derived from material, labor, and equipment coefficients, primarily governed in Indonesia by the Indonesian National Standard (SNI) and the Unit Price Analysis (AHSP) frameworks. Knowledge Gap: Variations in labor and material index coefficients across regulatory standards frequently yield substantial discrepancies in total project valuation, necessitating direct empirical evaluation on specific structural typologies such as multi-story hospital elevator shafts. Aims: This study compares construction cost estimates calculated using the SNI 2008 and AHSP 2023 methods for the three-story elevator shaft substructure project at RSUD Pindad Turen, Malang Regency. Results: Quantitative calculations based on working drawings, work volumes, and 2025 Malang Regency wage and material rates reveal that the AHSP 2023 method generates a total physical construction cost of IDR 356,370,000, whereas the SNI 2008 method yields IDR 552,075,000, demonstrating a cost difference of IDR 195,705,000 or 35% due to lower labor and material coefficients in AHSP 2023. Novelty: This research provides a direct comparative benchmark applying updated SE Menteri PUPR 2023 coefficients against SNI 7394:2008 specifically for reinforced concrete hospital elevator shaft substructures. Implications: Selecting the AHSP 2023 framework enables project owners and contractors to establish more economical, realistic, and accountable budget allocations for vertical transportation infrastructure.
Key Findings Highlights
- Unit price analysis using AHSP 2023 produces an economical budget of IDR 356,370,000 compared to IDR 552,075,000 under SNI 2008.
- Variations in labor and material index coefficients generate a total budget discrepancy of IDR 195,705,000 or 35% between the two calculation standards.
- Reinforced concrete structural work dominates expenditure in both budgeting standards, with lower worker and material indices in AHSP 2023 driving overall cost efficiency.
Keywords Construction Cost Estimation, Unit Price Analysis, Reinforced Concrete Structure, Budget Plan Comparison, Vertical Transportation Infrastructure
References
D. S. Adhy, Rencana Anggaran Biaya (Construction Cost Estimate). Jakarta, Indonesia: Gramedia Pustaka Utama, 2004.
K. A. Ratag, G. Y. Malingkas, dan J. Tjakra, “Perbandingan Rencana Anggaran Biaya antara Metode SNI dengan Metode AHSP pada Proyek Gedung Pendidikan Fakultas Teknik,” Jurnal TEKNO, vol. 19, no. 79, pp. 299–305, Dec. 2021.
Widiasanti dan Lenggogeni, Manajemen Konstruksi. Bandung, Indonesia: PT Remaja Rosdakarya, 2013, pp. 1–2, 17–18.
S. Soedrajat, Analisa (Cara Modern) Anggaran Biaya Pelaksanaan Lanjutan. Bandung, Indonesia: Nova, 1984.
K. A. Akhirson, Pengantar Manajemen Proyek. Depok, Indonesia: Universitas Gunadarma, 2004.
T. M. A. Kautsar, “Perhitungan RAB Perbandingan Metode BOW, SNI, dan Kontraktor,” Jurnal Teknik, vol. 136, no. 1, pp. 23–42, 2014.
Kementerian Pekerjaan Umum dan Perumahan Rakyat Republik Indonesia, Surat Edaran Menteri PUPR Nomor 73/SE/Dk/2023 tentang Tata Cara Penyusunan Perkiraan Biaya Pekerjaan Konstruksi. Jakarta, Indonesia: Kementerian PUPR, 2023.
Badan Standardisasi Nasional, SNI 7394:2008: Tata Cara Perhitungan Harga Satuan Pekerjaan Beton untuk Konstruksi Bangunan Gedung dan Perumahan. Jakarta, Indonesia: Badan Standardisasi Nasional, 2008.
M. A. Mufaris, F. Prihesnanto, dan E. Darma, “Perbandingan Estimasi Anggaran Biaya antara Metode BOW, SNI, dan Kontraktor pada Proyek Rumah Susun Pulogebang Jakarta Timur,” Jurnal Teknik Sipil, pp. 1–18, 1994.
J. A. Mukomoko, Dasar Penyusunan Anggaran Biaya Bangunan. Jakarta, Indonesia: Gaya Media Pratama, 1985.
Nasrul, Studi Analisa Harga Satuan Pekerjaan Beton dengan Metode BOW, SNI, dan Lapangan pada Proyek Irigasi Batang Anai II. Padang, Indonesia: Institut Teknologi Padang, 2013.
J. W. Niron, Pedoman Praktis Anggaran dan Borongan Rencana Anggaran Biaya Bangunan. Jakarta, Indonesia: Asona, 1992.
F. Novel, L. B. F. Sompie, dan G. Y. Malingkas, “Perencanaan Biaya dengan Menggunakan Perhitungan Biaya Nyata pada Proyek Perumahan (Studi Kasus Perumahan Green Hill Residence),” Jurnal Sipil Statik, vol. 2, no. 2, pp. 73–80, 2014.
B. Harsono, “Penerapan Rekayasa Nilai pada Proyek Pembangunan Rumah Sakit Umum Citra Medika Kecamatan Tarik Kabupaten Sidoarjo,” M.T. thesis, Dept. Civil Eng., Institut Teknologi Sepuluh Nopember, Surabaya, Indonesia, 2007.
M. T. Wahyudi, A. A. G. A. Yana, dan I. G. N. O. Suputra, “Analisis Perbandingan Rencana Anggaran Biaya dengan Metode SNI dan AHSP pada Proyek Konstruksi Gedung,” Jurnal Spektran, vol. 9, no. 2, pp. 145–153, Jul. 2021, doi: 10.24843/SPEKTRAN.2021.v09.i02.p06.
Downloads
Published
Issue
Section
Categories
License
Copyright (c) 2026 Salsabila Bintang Kirana, Budwi Harsono

This work is licensed under a Creative Commons Attribution 4.0 International License.