Implementation of Autonomous Maintenance in Total Productive Maintenance Implementasi Autonomous Maintenance Dalam Penerapan Total Productive Maintenance

Main Article Content

Juli Guritno
Atikha Sidhi Cahyana

Abstract

The purpose of this research is to increase the Avaibility rate, Performance rate and OEE value on pipe extruder line 9 at PT. Wahana Tunas Utama Rucika which is engaged in manufacturing PVC pipe products (Poly Vinyl Clhoride). In order to increase productivity, Total Productive Maintenance (TPM) is measured by calculating OEE. The method used in solving this problem the 8 pillars of TPM with the Autonomous Maintenance (AM) method. The implementation of the TPM pillar aims to increase the knowledge, responsibility and skills of production operators related to machines, so that overall productivity will increase. AM uses a structured and documented system so that this program can run consistently. The results of the implementation of the proposed improvements showed that the Availability rate had to increase by 3.61%, the Performance rate had to increase by 3.41% and OEE had to increase by 3.25% after the proposed improvements 6 months.

Downloads

Download data is not yet available.

Article Details

How to Cite
[1]
J. Guritno and A. Sidhi Cahyana, “Implementation of Autonomous Maintenance in Total Productive Maintenance”, PELS, vol. 1, no. 2, Jul. 2021.
Section
Industrial Engineering
Author Biography

Juli Guritno, Universitas Muhammadiyah Sidoarjo

Program Studi Teknik Industri, Fakultas Sains dan Teknologi

References

[1] A. Achyari, Materi Pokok Manajemen Operasi, 2nd ed. Tangerang Selatan: Universitas Terbuka, 2017.
[2] M. B. Anthony, “Analisis Penerapan Total Productive Maintenance (TPM) Menggunakan Overall Equipment Efectiveness (OEE) Dan Six Big Losses Pada Mesin Cold Leveller PT. KPS,” JATI UNIK : Jurnal Ilmiah Teknik dan Manajemen Industri, vol. 2, no. 2, pp. 94–103, Apr. 2019, doi: 10.30737/jatiunik.v2i2.333.
[3] J. A. Brydson, Plastics Materials, 7th ed. United Kingdom: Butterworths-Heinemann, 1999.
[4] N. Hairiyah, R. Rizki, and R. A. Wijaya, “ANALISIS TOTAL PRODUCTIVE MAINTENANCE (TPM) PADA STASIUN KERNEL CRUSHING PLANT (KCP) DI PT. X,” Jurnal Teknologi Pertanian Andalas, vol. 23, no. 1, pp. 103–110, Mar. 2019, doi: 10.25077/jtpa.23.1.103-110.2019.
[5] A. A. Hamza, “Analisa Total Productive Maintenance Dengan Menggunakan Metode Overall Equipment Effectiveness Di PT Karung Emas,” Matrik : Jurnal Manajemen dan Teknik Industri Produksi, vol. 16, no. 1, pp. 33–50, Sep. 2018, doi: 10.30587/matrik.v16i1.550.
[6] J. M. Tupan, A. Simanjuntak, and L. Aditiar, “Evaluasi Efektivitas Pemeliharaan Menggunakan Alat Reminder Pemeliharaan dengan Penerapan Total Productive Maintenance di PT. PLN (Persero) Rayon Haruku,” ARIKA, vol. 12, no. 1, pp. 25–40, Mar. 2018, doi: 10.30598/arika.2018.12.1.25.
[7] E. Krisnaningsih, “USULAN PENERAPAN TPM DALAM RANGKA PENINGKATAN EFEKTIFITAS MESIN DENGAN OEE SEBAGAI ALAT UKUR DI PT XYZ,” PROSISKO: Jurnal Pengembangan Riset dan Observasi Sistem Komputer, vol. 2, no. 2, Sep. 2015.
[8] S. Nakajima, Introduction to TPM: Total Productive Maintenance. New York: Productivity Press, 1988.
[9] N. H. Sari, Material Teknik. Yogyakarta : Deepublish, 2018.
[10] N. C. Dewi and D. I. Rinawati, “ANALISIS PENERAPAN TOTAL PRODUCTIVE MAINTENANCE (TPM) DENGAN PERHITUNGAN OVERALL EQUIPMENT EFECTIVENESS (OEE) DAN SIX BIG LOSSES MESIN CAVITEC PT. ESSENTRA SURABAYA (STUDI KASUS PT. ESSENTRA),” Industrial Engineering Online Journal, vol. 4, no. 4, 2015.
[11] M. P. Stephens, Productivity and Reliability-Based Maintenance Management. United States: Purdue University Press, 2010.
[12] M. Tajiri and F. Gotō, TPM Implementation, a Japanese Approach. United States: McGraw-Hill, 1992.
[13] M. W. Wakjira and A. S. Iyengar, “Autonomous Maintenance: A Case Study on Assela Malt Factory,” Bonfring International Journal of Industrial Engineering and Management Science, vol. 4, no. 4, pp. 170–178, Nov. 2014, doi: 10.9756/BIJIEMS.10364.