Development of Overhaul Maintenance Strategy Gas Turbin Series M701D at PLTGU Ubp Grati

Pengembangan Strategi Pemeliharan Overhoul Pada Gas Turbin Seri M701D Pada PLTGU Ubp Grati

Authors

  • Rizky Hernanda Pramudya Rizky Fakultas Sains dan Teknologi, Program Studi Teknik Mesin, Universitas Muhammadiyah Sidoarjo
  • Iswanto Fakultas Sains dan Teknologi, Program Studi Teknik Mesin, Universitas Muhammadiyah Sidoarjo

DOI:

https://doi.org/10.21070/pels.v10i1.3046

Keywords:

Brayton Cycle, Efficiency, Gas Turbine, Overhaul Maintenance, Power Plant Performance

Abstract

General Background Gas turbine power plants play a pivotal role in maintaining electrical grid stability through reliable combined-cycle generation. Specific Background Heavy-duty gas turbines operating under continuous thermal and mechanical stress require systematic inspection and maintenance to sustain operational parameters. Knowledge Gap While thermodynamic evaluations based on the Brayton cycle are common, comprehensive empirical evaluations quantifying post-overhaul performance gains specifically for the M701D series gas turbine remain limited. Aims This study evaluates the thermal performance, component efficiencies, and power output of an M701D series gas turbine at PLTGU UBP Grati before and after a major overhaul inspection. Results Thermodynamic calculations under a 100.25 MW operational load demonstrate an increase in compressor efficiency from 80.19% to 80.98% and turbine efficiency from 44.84% to 45.50%, alongside a reduction in heat input from 354.70 MW to 345.37 MW. Novelty A detailed Brayton cycle analysis demonstrates that rotor replacement and comprehensive turbine cleaning directly improve overall thermal efficiency. Implications These findings provide essential empirical data for power plant management to optimize maintenance schedules and improve overall operational productivity.

Key Findings Highlights

Turbine Inspection Increases Compressor Efficiency To 80.98%

System Overhaul Reduces Thermal Heat Input To 345.37 MW

Rotor Replacement Significantly Improves Overall Brayton Cycle Performance

Keywords Brayton Cycle, Efficiency, Gas Turbine, Overhaul Maintenance, Power Plant Performance

Downloads

Download data is not yet available.

References

R. Rizki, "Desain konsep Smart Electricity 4.0, bisnis model baru PT PLN (Persero) dengan memadukan layanan kelistrikan dan layanan internet PT PLN ICON+ berbasis Powerline Carrier Communication," Jurnal Ketenagalistrikan, no. 6, pp. 0–6, 2022.

M. Ridwan and F. Wibisono, "Analysis of Brayton cycle efficiency at 100 MW load before and after overhaul of Unit 1 Block 1 at PLTGU PT PLN Nusantara Power UP Gresik," Journal of Engineering and Technology, vol. 2, pp. 1540–1547, 2024.

R. Fahruddin, A. R. Fahruddin, M. I. N. Fadillah, and F. Firdaus, "Steam turbine performance variation based on operational parameters," Indonesian Journal of Innovation Studies, vol. 27, no. 1, pp. 1–16, 2026, doi: 10.21070/ijins.v27i1.2086.

V. Antono, R. A. Diantari, and Kriswanto, "Kajian kelayakan penambahan Fuel Gas Heater gas turbin tipe M701D untuk meningkatkan efisiensi PLTGU Grati," Jurnal Teknik Energi, pp. 56–61, 2015.

L. Nuraini, "Analisis keandalan dengan metode FMECA pada sistem distribusi PT PLN ULP Daruba Maluku Utara," Jurnal Teknik Elektro, 2024.

M. R. A. S., M. Ramdhani, and A. Miming, "Peranan Heat Recovery Steam Generator (HRSG) pada pembangkit listrik PLTGU," Jurnal Energi Listrik, vol. 3, no. 1, pp. 31–38, 2025.

R. Zulfikar, R. M. Zulfikar, and F. Firdaus, "RCM II identifies critical GTG components and maintenance strategy," Indonesian Journal of Innovation Studies, vol. 26, no. 4, pp. 10–20, 2025, doi: 10.21070/ijins.v26i4.2131.

P. Adhe, "Evaluasi kinerja turbin gas pada sistem PLTG di PT PLN Sektor Tello," Jurnal Teknik Mesin, 2018.

N. Gusnita and K. S. Said, "Analisa efisiensi dan pemanfaatan gas buang turbin gas Alsthom pada pembangkit listrik tenaga gas kapasitas 20 MW," Jurnal Teknologi Energi, vol. 14, no. 2, pp. 209–218, 2017.

P. S. M. Silitonga, "Analisis termodinamika terhadap kinerja Pembangkit Listrik Tenaga Gas dan Uap (PLTGU)," Jurnal Konversi Energi, 2022.

B. K. Utama, S. D. N. Laksana, and M. I. H. Pratama, "Exergy and energy analysis of heavy-duty gas turbine under varying ambient temperature conditions," Case Studies in Thermal Engineering, vol. 55, art. no. 104112, 2024, doi: 10.1016/j.csite.2024.104112.

H. Zhang, Y. Wang, and Z. Liu, "Performance degradation evaluation and predictive maintenance strategy for combined cycle gas turbine power plants," Energy, vol. 288, art. no. 129845, 2024, doi: 10.1016/j.energy.2023.129845.

R. K. Sahoo and P. K. Das, "Thermodynamic optimization and off-design performance analysis of M701D gas turbine in combined cycle operation," Applied Thermal Engineering, vol. 236, art. no. 121580, 2024, doi: 10.1016/j.applthermaleng.2023.121580.

M. T. Fadhil, A. S. Ahmad, and M. Z. Abdullah, "Impact of compressor blade fouling and washing frequency on heavy-duty gas turbine efficiency," Journal of Cleaner Production, vol. 434, art. no. 140211, 2025, doi: 10.1016/j.jclepro.2024.140211.

S. C. Mohapatra and B. B. Sahoo, "Comparative evaluation of maintenance strategies on the availability and heat rate of combined cycle gas turbine plants," Reliability Engineering & System Safety, vol. 241, art. no. 109678, 2025, doi: 10.1016/j.ress.2024.109678.

Downloads

Published

2026-10-15

How to Cite

[1]
R. H. P. Rizky and I. I. S. M. Iswanto, “Development of Overhaul Maintenance Strategy Gas Turbin Series M701D at PLTGU Ubp Grati: Pengembangan Strategi Pemeliharan Overhoul Pada Gas Turbin Seri M701D Pada PLTGU Ubp Grati”, PELS, vol. 10, no. 1, pp. 500–517, Oct. 2026.